After spending most of 2017 building our new house we now need to concentrate on running the business to ensure we can pay for it
1st March tomorrow is our opening day for the 2018 summer season It's mid afternoon and won't get any warmer today - present temperature - 3C -
Because of the weather I have spent much of this week persuading caravan owners not to visit to turn on their mains water as it will almost certainly freeze and cause inconvenience or expense - or both.
We will extend a warm welcome to all our customers but..... maybe in a couple of weeks time
We operate two small holiday caravan parks in the north-west corner of Worcestershire near Tenbury Wells. Some of the caravans are privately owned and others are let for family holidays. All caravans have fully fitted kitchens and bathrooms and are connected to mains electricity and water. Most have two bedrooms and sleep up to a maximum of four people. We pride ourselves on our personal welcome and customer care
Wednesday 28 February 2018
Wednesday 28 June 2017
New House at St Michaels
This is the mobile home we have had for six years
28June 2017 - concrete has arrived - and they are going back for more
Close of play on Thursday 6th July and the floor is taking shape
7th July 2017 - after three weeks it looks like this.
The timber frame arrives shortly.
12th July 2017
It's beginning to take shape.
We can see the ground floor rooms and the timber frame arrives tomorrow
This is Sandra in her new kitchenn
13th July
The timber frame has arrived
14th July - close of play week 4 and the walls are taking shape
18th July and I've been inside
19th July and the bedroom walls are up
Photos dated July 29th 2017
17th August and photo evidence of progress is slower
The screed has been poured this week so access to the ground floor is not possible - but slates are beginning to show on the roof
And now we are getting on to the windows doors and internals
In late May we separated the two halfs and moved it to Wigley Orchard - leaving a concrete pad which had to be broken up and carted away and the site clear for builders to start work on 19/6/2017
Unfortunately, the trench nearest the hedge did not comply with the insurer and had to be excavated a further metre deep. This led to the concrete pouring being delayed until 28th June. We prayed for dry weather overnight as the extra depth of the trench was finding water. More water would have caused problems. Although it did rain - it was not much so our praying must have worked.
This is the story so far - to be continued 28June 2017 - concrete has arrived - and they are going back for more
4th July update
5th July update
Walls? + some concrete beams are here
Close of play on Thursday 6th July and the floor is taking shape
7th July 2017 - after three weeks it looks like this.
The timber frame arrives shortly.
12th July 2017
It's beginning to take shape.
We can see the ground floor rooms and the timber frame arrives tomorrow
This is Sandra in her new kitchenn
13th July
The timber frame has arrived
14th July - close of play week 4 and the walls are taking shape
18th July and I've been inside
19th July and the bedroom walls are up
Photos taken Sunday 23rd July 2017
and upstairs for my first visit
En-suite bathroom from main bedroom
main bathroom
Sandra's office
The ground floor with added insulation
Photos dated July 29th 2017
7th August and the roof is taking shape
The screed has been poured this week so access to the ground floor is not possible - but slates are beginning to show on the roof
Photo 22/8/2017 and there are more slates on the roof
And now we are getting on to the windows doors and internals
14th October 2017
The new floor in hallway
Ducting for heating systems
house without the scaffolding from south west
house without the scaffolding from north west
house without the scaffolding from north
15th October 2017
Guest bathroom
Guest bathroom
my bathroom
my bathroom
kitchen with some new oak floor in place
kitchen cooker plug + sockets
gable end and blue sky
front door
Subscribe to:
Posts (Atom)